Magic Precision's staff is always on top of the project and regularly sends out project status reports to customers in clearly laid out format.
|
Tooling Manufacture Schedule |
|||||
| Customer | Happy Customer | |||||
| Part No. | R860701, R860702 (Zinc) | |||||
| Part Name | M HSNG FNT, M HSNG BACK (Zinc) | |||||
| Date | 9/14/2009 | |||||
| Procedure | May | June | ||||
| Tooling Design | 5/12~5/15 | |||||
| Design Complete/Approval | 5/15~5/17 | |||||
| Tooling Material Preparation | 5/18~5/20 | |||||
| Tool base Machining | 5/21~5/23 | |||||
| Heat treatment | 5/24~5/26 | |||||
| Electrode Machining | 5/27~5/29 | |||||
| Tool Insert fine Machining | 5/30~6/2 | 5/30~6/2 | ||||
| EDM | 6/3~6/5 | |||||
| Polishing | 6/6~6/8 | |||||
| Die fitting | 6/10~6/11 | 6/10~6/11 | ||||
| Assembly | 6/12~6/14 | |||||
| Tool Trial | 6/15~6/16 | |||||
| Machining + Painting | 6/17~6/25 | |||||